Text
The rules and regulations, ordinances, or resolutions adopted pursuant to O.C.G.A. 12-7-1 et. seq. for the purpose
of governing land-disturbing activities shall require, as a minimum, protections at least as stringent as the state
general permit; and best management practices, including sound conservation and engineering practices to
prevent and minimize erosion and resultant sedimentation, which are consistent with, and no less stringent than,
those practices contained in the Manual for Erosion and Sediment Control in Georgia published by the Georgia Soil
and Water Conservation Commission as of January 1 of the year in which the land-disturbing activity was
permitted, as well as the following:
269 | P a g e
Article Ten. Erosion Control and Stormwater Management
1. Stripping of vegetation, regrading and other development activities shall be conducted in a manner so as
to minimize erosion;
2. Cut-fill operations must be kept to a minimum;
3. Development plans must conform to topography and soil type so as to create the lowest practicable
erosion potential;
4. Whenever feasible, natural vegetation shall be retained, protected, and supplemented;
5. The disturbed area and the duration of exposure to erosive elements shall be kept to a practicable
minimum;
6. Disturbed soil shall be stabilized as quickly as practicable;
7. Temporary vegetation or mulching shall be employed to protect exposed critical areas during
development;
8. Permanent vegetation and structural erosion control practices shall be installed as soon as practicable;
9. To the extent necessary, sediment in run-off water must be trapped by the use of debris basins, sediment
basins, silt traps, or similar measures until the disturbed area is stabilized. As used in this paragraph, a
disturbed area is stabilized when it is brought to a condition of continuous compliance with the
requirements of O.C.G.A. 12-7-1 et. seq.;
10. Adequate provisions must be provided to minimize damage from surface water to the cut face of
excavations or the sloping of fills;
11. Cuts and fills may not endanger adjoining property;
12. Fills may not encroach upon natural watercourses or constructed channels in a manner so as to adversely
affect other property owners;
13. Grading equipment must cross flowing streams by means of bridges or culverts except when such
methods are not feasible, provided, in any case, that such crossings are kept to a minimum;
14. Land-disturbing activity plans for erosion, sedimentation and pollution control shall include provisions for
treatment or control of any source of sediments and adequate sedimentation control facilities to retain
sediments on-site or preclude sedimentation of adjacent waters beyond the levels specified in Section
1004.02(2) of this Article;
15. Except as provided in paragraph (16) and (17) of this subsection, there is established a 25 foot buffer
along the banks of all state waters, as measured horizontally from the point where vegetation has been
wrested by normal stream flow or wave action, except where the Director determines to allow a variance
that is at least as protective of natural resources and the environment, where otherwise allowed by the
Director pursuant to O.C.G.A. 12-2-8, where a drainage structure or a roadway drainage structure must be
constructed, provided that adequate erosion control measures are incorporated in the project plans and
specifications, and are implemented; or along any ephemeral stream. As used in this provision, the term
'ephemeral stream' means a stream: that under normal circumstances has water flowing only during and
for a short duration after precipitation events; that has the channel located above the ground-water table
year round; for which ground water is not a source of water; and for which runoff from precipitation is the
primary source of water flow. Unless exempted as along an ephemeral stream, the buffers of at least 25
feet established pursuant to part 6 of Article 5, Chapter 5 of Title 12, the "Georgia Water Quality Control
Act", shall remain in force unless a variance is granted by the Director as provided in this paragraph. The
following requirements shall apply to any such buffer:
a. No land-disturbing activities shall be conducted within a buffer and a buffer shall remain in its
natural, undisturbed state of vegetation until all land-disturbing activities on the construction site
are completed. Once the final stabilization of the site is achieved, a buffer may be thinned or
trimmed of vegetation as long as a protective vegetative cover remains to protect water quality
and aquatic habitat and a natural canopy is left in sufficient quantity to keep shade on the stream
bed; provided, however, that any person constructing a single-family residence, when such
residence is constructed by or under contract with the owner for his or her own occupancy, may
270 | P a g e
Article Ten. Erosion Control and Stormwater Management
thin or trim vegetation in a buffer at any time as long as protective vegetative cover remains to
protect water quality and aquatic habitat and a natural canopy is left in sufficient quantity to
keep shade on the stream bed; and
b. The buffer shall not apply to the following land-disturbing activities, provided that they occur at
an angle, as measured from the point of crossing, within 25 degrees of perpendicular to the
stream; cause a width of disturbance of not more than 50 feet within the buffer; and adequate
erosion control measures are incorporated into the project plans and specifications and are
implemented: (i) Stream crossings for water lines; or (ii) Stream crossings for sewer lines; and
16. There is established a 50 foot buffer as measured horizontally from the point where vegetation has been
wrested by normal stream flow or wave action, along the banks of any state waters classified as "trout
streams" pursuant to Article 2 of Chapter 5 of Title 12, the “Georgia Water Quality Control Act", except
where a roadway drainage structure must be constructed ; provided, however, that small springs and
streams classified as trout streams which discharge an average annual flow of 25 gallons per minute or
less shall have a 25 foot buffer or they may be piped , at the discretion of the landowner, pursuant to the
terms of a rule providing for a general variance promulgated by the Board, so long as any such pipe stops
short of the downstream landowner’s property and the land-owner complies with the buffer requirement
for any adjacent trout streams. The Director may grant a variance from such buffer to allow land-
disturbing activity, provided that adequate erosion control measures are incorporated in the project plans
and specifications and are implemented. The following requirements shall apply to such buffer:
a. No land-disturbing activities shall be conducted within a buffer and a buffer shall remain in its
natural, undisturbed, state of vegetation until all land-disturbing activities on the construction
site are completed. Once the final stabilization of the site is achieved, a buffer may be thinned or
trimmed of vegetation as long as a protective vegetative cover remains to protect water quality
and aquatic habitat and a natural canopy is left in sufficient quantity to keep shade on the stream
bed; provided, however, that any person constructing a single–family residence, when such
residence is constructed by or under contract with the owner for his or her own occupancy, may
thin or trim vegetation in a buffer at any time as long as protective vegetative cover remains to
protect water quality and aquatic habitat and a natural canopy is left in sufficient quantity to
keep shade on the stream bed; and
b. The buffer shall not apply to the following land-disturbing activities, provided that they occur at
an angle, as measured from the point of crossing, within 25 degrees of perpendicular to the
stream; cause a width of disturbance of not more than 50 feet within the buffer; and adequate
erosion control measures are incorporated into the project plans and specifications and are
implemented: (i) Stream crossings for water lines; or (ii) Stream crossings for sewer lines.
17. Nothing contained in O.C.G.A. 12-7-1 et. set. shall prevent any Local Issuing Authority from adopting rules
and regulations, ordinances, or resolutions which contain stream buffer requirements that exceed the
minimum requirements in Section 1004.02 and Section 1004.03 of this Article.
18. The fact that land-disturbing activity for which a permit has been issued results in injury to the property of
another shall neither constitute proof of nor create a presumption of a violation of the standards
provided for in Division 1 of this Article or the terms of the permit.